Speller meeting

What is needed for a new release:

Installer

There’s a separate document containing the test results for different combinations of MS Office and Windows versions.

DONE:

TODO:

POSTPONED:

PLX conversion

Remaining PLX bugs:

Second PRI

WE HAVE TO TALK ABOUT THE FOLLOWING:

Strange PLX behaviour  
Mihkalmas-beaivi 593

It seems that the lexical entry Mihkalmasbeaivi blocks the dynamic compound Mihkalmas-beaivi. This suggest a strange bug in the PLX code somewhere, but we don’t know where and how - yet. Needs to be investigated.

Thomas will add some more test words to try to help find the issue with this bug.

REGRESSIONS    
doesn’t follow cmp-tags OR vowel-shortening searvipresideanta > searvepresideanta sámediggepresideanta Sámediggeáirrasin 489
alphabet as non-first compound part & suggested CV-s 913

Second Last PRI

Bugs from here on can be left out of the next release if we are short on time.

WHY HYPHEN?      
birgen- birget+V+IV+Der/NomAct+N+SgCmp+RCmpnd birgen-nai 637 FIXED

  | Compounds | — | num cmp:s on 0- | 051-nummarat | 631 | non-ex. word accepted | saame | 658

Last PRI

  | Capitals | — | doesn’t understand caps | 1700-LOHKU | 647

  | REGRESSION | — | not recognized anymore recognized | biilarievttijođiheaddjái | 819 | FIXED

REGRESSION

Compounds

| imposs” cmps along w num. | 0-geažideapmigárvu (geažideapmigárvu is impossible) | 536,1145 | NO SUGGESTIONS - GOOD - BUT: | imposs” cmps sákkasteapmifierbmi> | (225) aseákkasteapmifierbmi ase- | 536 | –”– | (225) asiákkasteapmifierbmi asi- | –”– | (225) ásaákkasteapmifierbmi ása- | –”– | (225) áseákkasteapmifierbmi áse- | –”– | (225) ásoákkasteapmifierbmi áso- | –”– | (225) ásuákkasteapmifierbmi ásu- | –”– | (221) ášoákkasteapmifierbmi ášo- | –”– | (221) ášuákkasteapmifierbmi ášu-

DONE:

TODO:

Release plan

The December 1 goal has passed, without meeting the targets. On the plus side is that the number of open PLX bugs have been greatly reduced, and Tomi are squashinhg PLX bugs all the time. It just takes more time than anticipated.

The installer was not easily solved by the WiX alternative - it turned out that the Greenlandic proofing tools installer has the same problems as we have.

Re-scheduling the release plan: